Kongsberg Maritime – EPC 2 units of Dehumidifier Containers

Challenge

Compass Energy was commissioned to provide a turnkey solution for two units of Dehumidifier Containers. The completed product shall be installed on FSO Gagak Rimang. This is a fast paced project and the management of the schedule of the project is of utmost importance.

Scope

Compass Energy was tasked to design two units of Dehumidifier Containers, procure the necessary equipment and fabricate the entire structure. All required drawings were submitted to Class and approved. Project management were evidenced in different phases of the job scope namely from engineering, construction and testing to delivery.

Benefit

The project was completed on time and was of the highest standard despite the tight time frame given. All tests were conducted successfully and the final product was delivered on schedule.